In the maintenance survey report, the question text for creating a service request is displayed in the confirmation contents
The checklist provide an option to create a service request. Depending on the answer to the follow-up question, the maintenance survey report can be displayed in three different ways.
Screenshots are available in the File tab.
Example
When the answer to the question is "No," the option is set to enable the creation of a service request
NO1. the answer to the question is "Yes" → no record is added in the maintenance survey report screen.(wr_id=1150004568)
NO2. if the answer to the question is "No Follow-up service request is displayed → Create a service request and complete the checklist → One record is added on the maintenance survey report screen, and "null" is displayed in the confirmation contents.(wr_id=1150004566)
NO3. answer "no" to the question → follow-up service request is displayed→Complete the checklist without creating a service request→One record is added on the maintenance survey report screen, and the confirmation remains blank.(wr_id=1150004565)
In the above example scenario, this should be the logical and correct behaviour. (This is our expectation from the system)
In NO2, the confirmation should not be null, but should indicate that a "service request was created".
In NO3, please do not add a record to the maintenance survey report (I do not want options that were not selected to be displayed in the record).